In this video, Mr. Rau shows you the individual steps of the load test with the RAU DPG02 TOUCH pressure tester.
Step by step
How the measurement is carried out
- Enter object / customer and inspector
- Fitting the single-pipe meter cap
- Connect Y-hose and test hose to DPG07
- Menu: “Load test Long-term pressure measurement ” and click on“Load test” and “PUMP”
- Tap“START” as soon as the test pressure of 1 bar is reached
- Automatic measuring sequence starts (5 minutes adjustment time for pressure equalization and 10 minutes test time)
- Measuring device beeps and test report is printed out automatically
- Print out by clicking on the printer symbol
Note: The leak test is carried out after the load test.